PMP Exam Question

Aligned with PMBOK 6th Edition®.

You have been working as engineer for many years in your organization just over a year ago, you were promoted to a project management role and assigned a very large project. Your team has over 400 team members from around the world. Your technical background did not prepare you for the work you are doing today. Most of your team members are virtual. Your current focus is on negotiating for the team members you already have been working with. In what project management process group are you currently engaged in?

a) Initiating.

b) Planning.

c) Executing.

d) Monitoring and controlling.

1 responses on "PMP Exam Question"

  1. PMP Solution

    During the Develop Team process we provide training and team building. Negotiation happens on the Acquire Resources process, which is carried out during the Executing process group. Therefore right answer is C. [PMBOK 6th edition, Page 332] [Project Resource Management].

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

© 2019 OpenPM.org - All Rights Reserved

Who’s Online

There are no users currently online