PMP Exam Question 99

Aligned with PMBOK 6th Edition®.

Configuration Management Activities :

In an IT development project, Jim, the project manager, is now selecting change control tools. Which of the following is NOT a configuration management activity to be considered?

A. Identification and selection of a configuration item
B. Information recording and reporting about each configuration item.
C. Configuration verification and configuration audits
D. Implement configuration activity responses.

1 responses on "PMP Exam Question 99"

  1. PMP Solution 99

    A. Identify configuration item is a configuration management activity considered when selecting change control tools which provides the basis for which the product configuration is defined and verified, products and documents are labeled, changes are managed, and accountability is maintained.
    B. Record and report configuration item status is a configuration management activity considered when selecting change control tools which that provides information on recording and reporting about each configuration item.
    C. Perform configuration item verification and audit ensure that the composition of a project’s configuration items is correct and that corresponding changes are registered, assessed, approved, tracked, and correctly implemented. This ensures that the functional requirements defined in the configuration documentation are met.
    Implement configuration activity responses is not a configuration management activity considered when selecting change control tools. Therefore, right answer is D. [PMBOK 6th edition, Page 118] [Project Integration Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of Bahia
© 2020 - All Rights Reserved.