PMP Exam Question 98

Aligned with PMBOK 6th Edition®.

Procurement Statement of Work :

Before contracting services in your project, a review of Terms of Reference (TOR) is needed. You found that TOR in your project includes the information that should not be there. Which of the following information is NOT part of TOR?

A. Specified coordination requirements of tasks required to be performed by a contractor.
B. Standard the contractor will fulfill.
C. Short list of qualified sellers.
D. Definition of the schedule for initial submission.

1 responses on "PMP Exam Question 98"

  1. PMP Solution 98

    A. Tasks the contractor is required to perform as well as specified coordination requirements., are part of TOR.
    B. Standards the contractor will fulfill that are part of TOR as well.
    D. Definition of the schedule for initial submission and the review/approval time required are part of TOR.

    The phrase terms of reference (TOR) is sometimes used when contracting for services in the Procurement Statement of Work. Similar to the procurement SOW, a TOR typically includes apart from A, B, D; data that needs to be submitted for approval, detailed list of all data and services that will be provided to the contractor by the buyer for use in performing the contract, if applicable. However, prequalified sellers are not part of Terms of Reference, they are documented in the Procurement Management Plan instead. Therefore, right answer is C. [PMBOK 6th edition, Page 478, 481] [Project Procurement Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of Samruddhi Sudhakar Shetty
Profile picture of Imen MLIKA
Profile picture of Muhammad Elemam
© 2020 - All Rights Reserved.