PMP Exam Question 97

Aligned with PMBOK 6th EditionĀ®.

PMP Changes :

Matt is managing a predictive construction project. A change has affected the performance of project work and an action is needed to realign it with the project management plan. What is the name for this type of action?

A. Corrective action.
B. Preventive action.
C. Defect repair.
D. Rework.

1 responses on "PMP Exam Question 97"

  1. PMP Solution 97

    B. Preventive action is an intentional activity that ensures the future performance of the project work is aligned with the project management plan.
    C. Defect repair is an intentional activity that modifies a nonconforming product or product component.
    D. Rework is an action taken to bring a defective or nonconforming component into compliance with requirements or specifications.

    Change requests are processed for review and disposition through the Perform Integrated Change Control process Changes may include but are not limited to: Preventive action, Corrective action and Defect repair. Corrective action is an intentional activity that realigns the performance of the project work with the project management plan. Therefore, right answer is A. [PMBOK 6th edition, Page 112] [Project Integration Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

Who’s Online

Profile picture of YOUSSEF
Profile picture of Jaime Alonso Candau
Ā© 2020 - All Rights Reserved.