PMP Exam Question 93

Aligned with PMBOK 6th Edition®.

Project Life Cycle Management :

Kim is managing a project in which Validate Scope process is not repeated iteratively and it takes place with each deliverable and phase review, whilst, in contrast, Control Scope process is an ongoing process. Which life cycle approach is used in Kim’s project?

A. Predictive life cycle.
B. Adaptive life cycle.
C. Incremental life cycle.
D. Agile life cycle.

January 3, 2020

1 responses on "PMP Exam Question 93"

  1. PMP Solution 93

    B and D. In an adaptive or agile life cycle, the sponsor and customer representatives should be continuously engaged with the project to provide feedback on deliverables as they are created and to ensure that the product backlog reflects their current needs. The two processes (Validate Scope and Control Scope) are repeated for each iteration.
    C. In an incremental life cycle, the deliverable is produced through a series of iterations that successively add functionality within a predetermined time frame. Therefore, the two processes (Validate Scope and Control Scope) are repeated also for each iteration.

    In a predictive life cycle, the project scope, time, and cost are determined in the early phases of the life cycle. In this case, Validate Scope occurs with each deliverable or phase review and Control Scope is an ongoing process. Therefore, right answer is A. [PMBOK 6th edition, Page 19, 131] [Project Scope Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

Who’s Online

There are no users currently online
© 2020 - All Rights Reserved.