PMP Exam Question 88

Aligned with PMBOK 6th Edition®.

Project Team Members

Tim is the project manager in the development of a new treatment. The scope of the work in Tim´s project has increased and, consequently, new project team members will be hired. Which of the following is the process of hiring new team members?

A. Develop Team process.
B. Acquire Team process.
C. Acquire Resources process.
D. Identify Resources process.

December 20, 2019

1 responses on "PMP Exam Question 88"

  1. PMP Solution 88

    Develop Team is the process of improving competencies, team member interaction, and the overall team environment to enhance project performance. Nonetheless, Acquire Resources is the process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work. The key benefit of this process is that it outlines and guides the selection of resources and assigns them to their respective activities. This process is performed periodically throughout the project as needed. Therefore, right answer is C. [PMBOK 6th edition, Page 416] [Project Resource Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

Who’s Online

Profile picture of Kurt
© 2020 - All Rights Reserved.