In a discussion about a technical solution, conflict between project team members arises. You, as project manager, should deal with the conflict resolution process. Which of the following documents include team values as well as conflict resolution processes in your project?

A. Resource Management Plan.
B. Team Charter.
C. Organizational Process Assets.
D. Enterprise Environmental Factors.