PMP Exam Question 79

Aligned with PMBOK 6th Edition®.

In the execution of a designing project of a toy, Alan has been hired recently as project manager. After his first month, he has received many requests from different stakeholders asking to provide project reports. What should Alan do first?

A. Alan should prepare and send the requested information.
B. Alan should delegate this request to the project team.
C. Alan should review the communications management plan.
D. Alan should discuss this with the project sponsor.

6 responses on "PMP Exam Question 79"

  1. PMP Solution 79

    First thing, Alan should review the stakeholder communication requirements in the communications management plan in order to determine whether the information should or should not be sent and, if the requests are legitimate, in order to know how project reports should be communicated. Therefore, the right choice for this question is C. [PMBOK 6th edition, Page 377] [Project Communication Management]

    Cheers

  2. Uh, don’t you mean answer C – Alan should review the communications management plan? Question asks what should Alan do first? Your answer states, First thing, Alan should review the stakeholder communications requirements in the communications management plan…” Answer D was Alan, should discuss this with project sponsor. Or should he discuss this with the project sponsor first?

  3. The Answer is C.

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

© 2019 OpenPM.org - All Rights Reserved

Who’s Online

There are no users currently online