Before the baselines of your IT development project are established, the project sponsor requires a major change in the project. You assessed him on the impacts that change would have in the project. Which of the following statements is true about this situation?

A. That change does not have to be formally controlled by the Perform Integrated Change Control process.
B. Any change in a configuration element should be formally controlled and will require a change request.
C. Formal integrated change control process is always required.
D. That change must be communicated to all stakeholders previously.

1 responses on "PMP Exam Question 77"

  1. PMP Solution 77

    Once the project is baselined, change requests go through this process. As a general rule, each project’s configuration management plan should define which project artifacts need to be placed under configuration control. Any change in a configuration element should be formally controlled and will require a change request, but this is not the case since the baselines are not yet established. Before the baselines are established, changes are not required to be formally controlled by the Perform Integrated Change Control process. Therefore, the right choice for this question is A. [PMBOK 6th edition, Page 115] [Project Integration Management]

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

© 2019 OpenPM.org - All Rights Reserved

Who’s Online

Profile picture of Silver Xc
Profile picture of Kevin
Profile picture of Wis
Profile picture of Francisco Muro