PMP Exam Question 76

Aligned with PMBOK 6th EditionĀ®.

The project of a dam is being managed by you. So you are now documenting specific actions to be performed to produce the project deliverables by setting milestones in the project schedule. Which of the following statements is true about milestones?

A. All milestones are mandatory by definition.
B. Milestones have zero duration.
C. Project charter does not include any information related to milestones, due to it is already in the project schedule.
D. Milestone charts are included in the project document called Milestone list.

4 responses on "PMP Exam Question 76"

  1. PMP Solution 76

    A milestone list identifies all project milestones and indicates whether the milestone is mandatory, such as those required by contract, or optional, such as those based on historical information. On the other hand, the Project Charter usually includes a summary milestone schedule. Nonetheless, a milestone chart is included in the Project schedule and not in the milestone list. So, milestones have zero duration because they represent a significant point or event. Therefore, the right choice for this question is B. [PMBOK 6th edition, Page 186] [Project Schedule Management]

    Cheers

  2. A milestone has a zero duration., or signifies a completion of schedule or summary tasks.

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

Ā© 2019 OpenPM.org - All Rights Reserved

Who’s Online

Profile picture of Narayan Agnihotri
Profile picture of Ilja Aljoskin
Profile picture of Jaime Alonso Candau