PMP Exam Question 71

Aligned with PMBOK 6th Edition®.

Your sponsor asked you for the projection of budget deficit or surplus at the completion of the project you manage (VAC). The future work will be completed at the planned rate, so the Budget at Completion is $10 million , the Actual Cost is $5 million and the Earn Value is $4 million. Which of the following statements is correct about your project?

A. Your project is under planned cost.
B. Your project is on planned cost.
C. Your project is over planned cost.
D. You need more information to find out about the cost situation.

October 16, 2019

2 responses on "PMP Exam Question 71"

  1. PMP Solution 71

    Variance at Completion is the projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion.The formula to calculate VAC is VAC = BAC – EAC. We know BAC but not EAC. If the future work will be accomplished at the planned rate, use; EAC = AC+BAC-EV; EAC=5M + 10M – 4M = 11M. So VAC= 10M – 11M = -1M. If VAC is positive then the project is under planned cost, if neutral on planned cost and if negative over planned cost. Therefore, the right choice for this question is C. [PMBOK 6th edition, Page 267] [Project Cost Management]

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

© 2019 OpenPM.org - All Rights Reserved

Who’s Online

There are no users currently online
top