PMP Exam Question 67

Aligned with PMBOK 6th EditionĀ®.

Risk Register

Jack is now documenting details of identified individual project risks in the risk register for his construction project. Which information should Jack NOT include in the risk register?

A. List of potential risk responses.
B. Potential risk owners.
C. List of identified risks.
D. Means for grouping individual project risk.

December 26, 2019

1 responses on "PMP Exam Question 67"

  1. PMP Solution 67

    Content of the risk register may include but is not limited to:
    -List of identified risks. Each individual project risk is given a unique identifier in the risk register.
    -Potential risk owners. Where a potential risk owner has been identified during the Identify Risks process, the risk owner is recorded in the risk register. This will be confirmed during the Perform Qualitative Risk Analysis process.
    -List of potential risk responses. Where a potential risk response has been identified during the Identify Risks process, it is recorded in the risk register. This will be confirmed during the Plan Risk Responses process. Nonetheless, means for grouping individual project risks is part of Risk Categories in the risk management plan. Therefore, the right choice for this question is D. [PMBOK 6th edition, Page 417] [Project Risk Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

Who’s Online

Profile picture of Ivy2020
Ā© 2020 - All Rights Reserved.