Tom, the project manager in the construction of a new factory, worked to create an environment to facilitate teamwork and motivate his team. Now, he states that team members are, according to the Tuckman ladder, in Adjourning phase. What does that mean?

A. It means that the team members have met and are learning about the project.
B. It means that the team performs as a well organized unit.
C. It means that the team has completed the work and moves on from Tom´s project.
D. It means that conflicts have affected team members´ professional relationship.

September 25, 2019

2 responses on "PMP Exam Question 65"

  1. PMP Solution 65

    The Tuckman ladder includes five stages; Forming, Storming, Norming, Performing and Adjourning. In Adjourning phase, the team completes the work and moves on from the project. This typically occurs when staff is released from the project as deliverables are completed or as part of the Close Project or Phase process. Therefore, right answer is C. [PMBOK 6th edition, Page 338] [Project Resource Management]

    Cheers

  2. Loving the information on this web site, you have done great job on the blog posts.

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

© 2019 OpenPM.org - All Rights Reserved

Who’s Online

Profile picture of Nadia Kardiolaka
top