PMP Exam Question 64

Aligned with PMBOK 6th EditionĀ®.

In the construction of a new skyscraper, Alex, the project manager, is now in the Define Activities process. Rolling wave planning has been of great help to Alex during this process. Which of the following statements is true about Rolling Wave Planning?

A. Rolling wave planning is a predictive planning technique that focused in detail schedule baseline development.
B. Rolling wave planning is a technique used for subdividing the project scope into work packages to set a schedule baseline.
C. For projects using rolling wave planning, the activity list must not be updated since the schedule baseline should be reviewed directly.
D. Rolling wave planning is an iterative planning technique in which work further in the future is planned at a higher level.

September 20, 2019

2 responses on "PMP Exam Question 64"

  1. PMP Solution 64

    Decomposition, and not rolling wave planning, is the technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts. For projects that use rolling wave planning or agile techniques, the activity list will be updated periodically as the project progresses. Rolling wave planning is an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work further in the future is planned at a higher level. Therefore, right answer is D. [PMBOK 6th edition, Page 185] [Project Schedule Management]

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

Ā© 2019 OpenPM.org - All Rights Reserved

Who’s Online

Profile picture of Guest
Profile picture of Suresh Kumar
top