PMP Exam Question 55

Aligned with PMBOK 6th Edition®.

Jim is engaging stakeholders in the refurbishment of a villa in Miami. He realized that managing the needs and expectations on this project is key to achieve success. When should Jim be most active for that?

A. Initiating and Planning.

B. Planning and Executing.

C. Executing and Controlling.

D. Controlling and Closing

3 responses on "PMP Exam Question 55"

  1. B. Planning and Executing.

  2. PMP Solution 55

    The ability of stakeholders to influence the final characteristics of the project’s product, without significantly impacting cost and schedule, is highest at the start of the project and decreases as the project progresses toward completion. The cost of making changes and correcting errors typically increases substantially as the project approaches completion. Therefore, it should be addressed as soon as possible and the solution to this question is A. [PMBOK 6th edition, Page 549] [Project Stakeholder Management]

    Cheers

  3. Answer is A.

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

There are no users currently online
top
© 2019 OpenPM.org - All Rights Reserved