Brat is managing a predictive construction project, he has just received the approved version of the work breakdown structure, the WBS dictionary and the Project Scope Statement. Which project document has Brat received?

A. Scope Baseline.

B. Validate Scope.

C. Plan Scope Management.

D. Definition of the Scope.

2 responses on "PMP Exam Question 51"

  1. PMP Solution 51

    Plan Scope Management and Validate Scope are not project documents, they are processes. In predictive projects, the scope baseline for the project is the approved version of the project scope statement, work breakdown structure (WBS), and its associated WBS dictionary. A baseline can be changed only through formal change control procedures. Therefore, right answer is A. [PMBOK 6th edition, Page 131] [Project Scope Management]

    Cheers

  2. Scope baseline is not project document, it is subsidiary project management plan. Am I wrong?

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

© 2019 OpenPM.org - All Rights Reserved

Who’s Online

Profile picture of Tamara
Profile picture of Yousuf Khan
Profile picture of tom
Profile picture of Jaekyo Seo
Profile picture of Sana Niazi
Profile picture of Ahmed