PMP Exam Question 50

Aligned with PMBOK 6th EditionĀ®.

Jackson is the project manager in the development of an electric car. Risk Register is quite long, so he decided to prioritize project risks by probability of occurrence and impact to focus efforts on high priority risks. What process is Jackson in?

A. Identify Risks.

B. Implement Risk Responses.

C. Perform Quantitative Risk Analysis.

D. Perform Qualitative Risk Analysis.

1 responses on "PMP Exam Question 50"

  1. PMP Solution 50

    Identify Risks process is about identifying individual project risks, overall project risk, and documenting them. On the other hand, Implement Risk Responses is the process of implementing agreed-upon risk response plans. Perform Quantitative Risk Analysis is the process of analyzing the combined effect of identified individual project risks.

    Perform Qualitative Risk Analysis is the process of prioritizing project risks for further analysis or action by assessing their probability of occurrence and impact. The key benefit of this process is that it focuses efforts on high-priority risks. Therefore, Jackson is in Perform Qualitative Risk Analysis and the right answer is D [PMBOK 6th edition, Page 419] [Project Risk Management]

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

There are no users currently online
top
Ā© 2019 OpenPM.org - All Rights Reserved