PMP Exam Question 5

Aligned with PMBOK 6th Edition®.

PMP Chart

For the first 24 months, your project progressed well, however, now the project schedule has been pulled in dramatically to address a change in the market. You would like to use a tool to make it clear who is the one person accountable for each activity. Most likely you will use a(n):

a) Organizational breakdown structure.

b) Project organizational chart.

c) Responsibility assignment matrix.

d) Resource calendar.

February 16, 2020

3 responses on "PMP Exam Question 5"

  1. PMP Solution 5

    An organizational breakdown structure shows the organization’s departments and which work packages are assigned to which department. On the other hand, organizational chart shows reporting relationships. A resource calendar shows when specific resources will become available. Responsibility assignment shows who is reponsible for what activity. It is critical that only one person be accountable for each activity. Therefore, right answer is c). [PMBOK 6th edition, Page 317] [Project Resource Management].

    Cheers

  2. C- Responsibility assignment matrix.

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of bootlog
Profile picture of Karthik
Profile picture of R P A Anbazhagan
Profile picture of Jose Cheung
Profile picture of Arvind

© 2020 - All Rights Reserved.
OpenPM.org contains affiliate links, meaning at no additional cost to you, we will earn a commision if you click through and make a purchase.
OpenPM has never and will never compromise its integrity.

1