PMP Exam Question 49

Aligned with PMBOK 6th EditionĀ®.

Steve is the project manager of the construction of a nuclear plant. He is mentoring one project team member by providing information about reactions to communications. Which communication technique is Steve using?

A. Coaching.

B. Feedback.

C. Training.

D. Focus groups.

1 responses on "PMP Exam Question 49"

  1. PMP Solution 49

    Coaching is not a technique included in PMBOK 6th edition. On the other hand, Training includes all activities designed to enhace the competencies of the project team members however is not a technique used in any Project Communications Management process. Focus groups is a technique that brings together prequalified stakeholders and subject matter experts to learn about their expectation about a product, service or results. Feedback is a tecnique used in Manage Communications process and it is the information about reactions to communications, a deliverable or a situation. Examples include coaching, mentoring and negotiating. Therefore, correct answer is B. [PMBOK 6th edition, Page 384] [Project Communications Management]

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

Profile picture of Maria Cristina Mason
top
Ā© 2019 OpenPM.org - All Rights Reserved