PMP Exam Question 48

Aligned with PMBOK 6th Edition®.

Your project sponsor asked you for the Estimate at Completion of your project. The approved budget for this project was 60,000 €, there have already been 40,000 € spent in the project, but the works completed are worth only 20,000 €. You are sure that the future work will be accomplished at the planned rate. What is the Estimate at Completion?

A. 40,000 €.

B. 60,000 €.

C. 80,000 €.

D. 100,000 €.

1 responses on "PMP Exam Question 48"

  1. PMP Solution 48

    If future work will be accomplished at the planned rate; EAC= AC + BAC – EV. In this case we have; AC = 40,000 €, BAC = 60,000 € and EV = 20,000 €. So EAC = 40,000 € + 60,000 € – 20,000 €= 80,000 €. Therefore, correct answer is C. [PMBOK 6th edition, Page 267] [Project Cost Management]

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

© 2019 OpenPM.org - All Rights Reserved

Who’s Online

There are no users currently online
top