PMP Exam Question 46

Aligned with PMBOK 6th Edition®.

George, as project manager of the construction of a theater, looks for the authority, responsibility and competency of project team members. In which document could George find this information?

A. Resource register.

B. Responsability Assignment Matrix.

C. Project team resource management.

D. Resource Management Plan.

1 responses on "PMP Exam Question 46"

  1. PMP Solution 46

    Project team resource management provides guidance on how project team resource should be defined, staffed, managed and eventually released. A Responsability Assignment Matrix (RAM) is a tool and technique and not a document that shows the project resources assigned to each work package. So this can not be the answer. Resource Management Plan provides guidance on how project resources should be categorized, allocated, managed and released. Roles and responsibilities in the Resource Management Plan contains all the information related to roles, authorities, responsibilities and competences. Therefore, correct answer is D. [PMBOK 6th edition, Page 318] [Project Resource Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

© 2019 OpenPM.org - All Rights Reserved

Who’s Online

Profile picture of Colin Foster
Profile picture of cohy