George, as project manager of the construction of a theater, looks for the authority, responsibility and competency of project team members. In which project document could George find this information?

A. Resource register.

B. Responsability Assignment Matrix.

C. Project team resource management.

D. Resource Management Plan.

February 16, 2020

1 responses on "PMP Exam Question 46"

  1. PMP Solution 46

    Project team resource management provides guidance on how project team resource should be defined, staffed, managed and eventually released. A Responsability Assignment Matrix (RAM) is a tool and technique and not a document that shows the project resources assigned to each work package. So this can not be the answer. Resource Management Plan provides guidance on how project resources should be categorized, allocated, managed and released. Roles and responsibilities in the Resource Management Plan contains all the information related to roles, authorities, responsibilities and competences. Therefore, correct answer is D. [PMBOK 6th edition, Page 318] [Project Resource Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of Jose Cheung
Profile picture of Varun Srivastava

© 2020 - All Rights Reserved.
OpenPM.org contains affiliate links, meaning at no additional cost to you, we will earn a commision if you click through and make a purchase.
OpenPM has never and will never compromise its integrity.

1