Tom is the project manager in the development of a new phone. He is now optimizing assembly of the design while defining the shape of the phone. He is focused on cost reduction and quality improvement. Which set of technical guidelines is Tom using?

A. Problem solving.

B. Design for X.

C. Quality reports.

D. Benchmarking.

1 responses on "PMP Exam Question 45"

  1. PMP Solution 45

    Quality reports are project documents in which the information presented may include all quality management issues escalated by the team; recommendations for process, project, and product improvements. Problem solving entails finding solutions for issues or challenges. It can include gathering additional information, critical thinking, creative, quantitative and/or logical approaches. On the other hand, Benchmarking involves comparing actual or planned project practices or the project’s quality standards to those of comparable projects to identify best practices, generate ideas. Design for X (DfX) is a set of technical guidelines that may be applied during the design of a product for the optimization of a specific aspect of the design. The X in DfX can be different aspects of product development, such as reliability, deployment, assembly, manufacturing, cost, service, usability, safety, and quality. Using the DfX may result in cost reduction, quality improvement, better performance, and customer satisfaction. Therefore, correct answer is B. [PMBOK 6th edition, Page 295] [Project Quality Management]

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

There are no users currently online
top
© 2019 OpenPM.org - All Rights Reserved