PMP Exam Question 41

Aligned with PMBOK 6th EditionĀ®.

You, as construction project manager, are concerned that builders are behind schedule, so you gather actual start and finish dates of schedule activities, key performance indicators (KPIs) and number of defects in your project. This will later be used as an input to;

A. Monitoring and controlling process group.

B. Direct and manage project work process.

C. Manage project knowledge process.

D. Define scope process.

1 responses on "PMP Exam Question 41"

  1. PMP Solution 41

    Examples of work performance data include work completed, key performance indicators (KPIs), technical performance measures, actual start and finish dates of schedule activities, story points completed, deliverables status, schedule progress, number of change requests, number of defects, actual costs incurred, actual durations, etc.The work performance data will also be used as an input to the Monitoring and Controlling Process Group, and can be used as feedback into lessons learned to improve the performance of future work packages. Therefore, right answer is A. [PMBOK 6th edition, Page 92, 95] [Project Integration Management]

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

Ā© 2019 OpenPM.org - All Rights Reserved

Who’s Online

There are no users currently online
top