PMP Exam Question 38

Aligned with PMBOK 6th Edition®.

John, as project manager, has decided to increase the number of resources to crash his project schedule. However, crashing does not always cut the time by half and, in worst cases, doubling resources assigned to an activity may increase the activity duration. This happens because of;

A. Additional risk introduced.

B. Student Syndrome.

C. Funding limit reconciliation.

D. Parkinson´s Law.

1 responses on "PMP Exam Question 38"

  1. PMP Solution 38

    Student Syndrome is a syndrome when people start to apply themselves only at the last possible moment before the deadline. Parkinson´s Law happens when work expands to fill the time available for its completion. The reason to increase the duration of an activity while crashing is due to additional risk introduced and at some point adding to many resources may increase duration due to knowledge transfer, learning curve, additional coordination and other factors involved. Therefore, correct answer is A. [PMBOK 6th edition, Page 197] [Project Schedule Management].

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

There are no users currently online
top
© 2019 OpenPM.org - All Rights Reserved