PMP Exam Question 37

Aligned with PMBOK 6th Edition®.

Alex is obtaining seller responses, selecting a seller and awarding a contract based in a competitive range as specify in the Plan Procurement Management. Will generally Alex need, before awarding a complex contract to a selected seller, the approval of any stakeholder?

A. No.

B. Yes, the approval of the customer.

C. Yes, the approval of the organizational senior management.

D. Yes, the approval of the project sponsor.

1 responses on "PMP Exam Question 37"

  1. PMP Solution 37

    Selected sellers are those who have been judged to be in a competitive range based on the outcome of the proposal or bid evaluation. Final approval of complex, high value, high risk procurements will generally require organizational senior management approval prior to award. Therefore, correct answer is C. [PMBOK 6th edition, Page 488] [Project Procurement Management].

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

© 2019 OpenPM.org - All Rights Reserved

Who’s Online

Profile picture of Yousuf Khan
Profile picture of tom
Profile picture of Jaekyo Seo
Profile picture of Sana Niazi
Profile picture of Ahmed