David has been hired as project manager of an IT implementation project. There has been several change requests that could have a major impact on project scope, cost and/or schedule. David evaluated the impact of changes and the Change Control Boards (CCB) has just approved the change requests. Nevertheless, the project sponsor is not a member of the CCB. What should David do next?

A. Ask for approval of the project sponsor.

B. Update project baselines.

C. Inform key stakeholders about changes to be carried out.

D. Implement the changes.

1 responses on "PMP Exam Question 36"

  1. PMP Solution 36

    These changes can require adjustments to the project management plan and other project documents. Customer or sponsor approval may be required for certain change requests after CCB approval, unless they are part of the CCB. Therefore, correct answer is A. [PMBOK 6th edition, Page 115] [Project Integration Management].

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

Ā© 2019 OpenPM.org - All Rights Reserved

Who’s Online

There are no users currently online
top