PMP Exam Question 33

Aligned with PMBOK 6th Edition®.

Jack is the project manager of an IT project. The sponsors of this project ask Jack if he can prepare a base document including expected tangible and intangible value to be gained by the implementation of the project. Which document do they ask Jack to prepare?

A. Project Benefits Management Plan.

B. Project Charter.

C. Project Business Case.

D. Project Success Measures.

June 3, 2019

1 responses on "PMP Exam Question 33"

  1. PMP Solution 33

    For the avoidance of doubt, business documents are inputs to Develop Project Charter process. So Project Charter incorporates information from business documents but they are not part of it. The Project Benefits Management Plan is the document that describes how and when the benefits of the project will be delivered and describes the mechanisms that should be in place to measure those benefits. It includes but is not limited to documenting;
    -Target benefits (e.g. the expected tangible and intangible value to be gained by the implementation of the project)
    The project sponsor is generally accountable for the development and maintenance of the Project Business Case Documents (including Project Business Case and Project Benefits Management Plan). However, the project manager is responsible for providing recommendations. Therefore right answer is A. [PMBOK 6th edition, Page, 33] [Introduction].

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

© 2019 OpenPM.org - All Rights Reserved

Who’s Online

Profile picture of Ali
Profile picture of Jaime Alonso Candau