PMP Exam Question 28

Aligned with PMBOK 6th EditionĀ®.

Project Stages

In an electric car design project, the PMO explains the new project manager the state of art of the project. PMO refers all their project management works has been based on PMBOK and that they are now back to a Pre-assignment stage. What is the project depandent of?

A. The project is dependant of the selection of a subcontrator.

B. The project is dependant of a specilist engineer.

C. The project is dependant of the approval of scope.

D. The project is dependant of the assignment of responsabilities to team member.

February 16, 2020

1 responses on "PMP Exam Question 28"

  1. PMP Solution 28

    The tool and technique used in the assignment of roles and responsabilities to team members is the Responsability Assignment Matrix and not Pre- assignment. Pre-assignment is a tool and technique of Acquire Resources process. This situation can occur if the project is the result of specific resources being identified as part of a competitive proposal or if the project is dependent upon the expertise of particular persons.Therefore, correct answer is B [PMBOK 6th edition, Page 333] [Project Resource Management].

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of kumar
Profile picture of Guest
Profile picture of Justyna
Ā© 2020 - All Rights Reserved.