PMP Exam Question 26

Aligned with PMBOK 6th EditionĀ®.

The construction of a new soccer stadium with you as project manager has a quality defect in some deliveries of floor tiles. It is required that you evaluate how that would affect the tiling works among others. Which type of graph is the most suitable to show the relationship between these two variables?

A. Flowchart.

B. Scatter diagrams.

C. Affinity diagram.

D. Matrix.

1 responses on "PMP Exam Question 26"

  1. PMP Solution 26

    Data representation techniques included in this question are:
    -Flowcharts show a series of steps that lead to a defect.
    -Affinity diagrams can organize potential causes of defects into groups showing areas that should be focused on the most.
    -A matrix diagram seeks to show the strength of relationships among factors, causes, and objectives that exist between the rows and columns that form the matrix.
    -A scatter diagram is a graph that shows the relationship between two variables. Scatter diagrams can demonstrate a relationship between any element of a process, environment, or activity on one axis (tiling works) and a quality defect on the other axis. Therefore right answer is B. [PMBOK 6th edition, Page 293] [Project Quality Management].

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

There are no users currently online
top
Ā© 2019 OpenPM.org - All Rights Reserved