PMP Exam Question 25

Aligned with PMBOK 6th Edition®.

A project of a new APP, with you as project manager, is being developed as planned. However, during one quality audit conducted by the PMO, one of your colleges recommend you an improvement of processes and procedures while executing the interface. Before taking any action, you want to analyze and evaluate yourself the opportunities for improvement. Which of the following tools are the two most common for quality improvement?

A. Salience method and Plan-do-check-act.

B. Data gathering and Six Sigma.

C. Plan-do-check-act and Six Sigma.

D. Data gathering and Salience method.

1 responses on "PMP Exam Question 25"

  1. PMP Solution 25

    Quality improvements can occur based on findings and recommendations from quality control processes, the findings of the quality audits, or problem solving. Plan-do-check-act and Six Sigma are two of the most common quality improvement tools used to analyze and evaluate opportunities for improvement. Therefore, the right answer is C.[PMBOK 6th edition, Page 296] [Project Quality Management].

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

info@openpm.org

© 2019 OpenPM.org - All Rights Reserved

Who’s Online

Profile picture of mah
Profile picture of Jaekyo Seo