James, as the Project Manager of a large construction project, notices that the project team has been together for a while, but not yet collaborating. He decides to engage the group with beginning to address actual project work and technical decisions moving the stage of team development from:

A. Forming to Performing.

B. Forming to Storming.

C. Storming to Norming.

D. Storming to Performing.

2 responses on "PMP Exam Question 24"

  1. PMP Solution 24

    In the Tuckamn ladder, within the Develop Team process, the 5 phases of development that teams may go through are; Foming, Storming, Norming, Performing and Adjourning. Performing is the phase in which teams reach the performing stage function as a well- organized unit. Norming is the phase in which team members begin to work together and adjust their work habits and behaviour to support the team. On the other hand, Forming is the phase where the team members meet and learn about the project and their formal roles and responsabilities and Storming is the phase in which the team begin to address project work, technical decisions and the project management approach. Therefore, the solution is B. moving from Forming to Storming.[PMBOK 6th edition, Page 338] [Project Resource Management]

    Cheers

  2. Q24: Isn’t it the case of storming to norming, As it is given that team is there for a while but they are not collaborating. which indicates people are having conflicts and issues with other team members. they are together but project work is suffering set back because of STORMING stage

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

There are no users currently online
top
Ā© 2019 OpenPM.org - All Rights Reserved