PMP Exam Question 23

Aligned with PMBOK 6th EditionĀ®.

A new airport is being built and you are the project manager. Since the beginning of the project, your customer has asked for installing the floor tiles of the ground floor level in a particular way, making an image when looking from upper levels. Which PMBOK term defines best the cost associated with the extra labour of installing the tiles that way?

A. Cost of Nonconformance.

B. Labour Costs.

C. Appraisal Costs.

D. Prevention Costs.

1 responses on "PMP Exam Question 23"

  1. PMP Solution 23

    Cost of Nonconformance is the money spent during and after the project termination because of failures. On the other hand, Labour Cost is not a PMBOK 6th Edition term. Appraisal Costs is a Cost of Conformance but used to asses quality for example with Testings or Inspections. This question asks for the time spent to build a quality product, precisely for the cost spent to build it right to meet customer expectations, therefore the right answer is D. [PMBOK 6th edition, Page 283] [Project Quality Management]

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

There are no users currently online
top
Ā© 2019 OpenPM.org - All Rights Reserved