PMP Exam Question 22

Aligned with PMBOK 6th EditionĀ®.

Cindy is part of a project management office (PMO). Her office is responsible for the centralized and coordinated management of 18 projects. Each project has its own project manager. Which of the following will not typically be a responsibility of her PMO?

A. Coaching, mentoring, training, and oversight.

B. Development of a detailed description of each project and the product it produces.

C. Managing shared resources across all the projects administered by the PMO.

D. Developing and managing project policies.

1 responses on "PMP Exam Question 22"

  1. PMP Solution 22

    The main function of a PMO is to support project managers in different ways. This may include developing and managing project policies, coaching, mentoring, training, and oversight. It also may include management of resources that are shared across the projects. However, development of a detailed description of each project would be a responsibility of the project manager handling the project, not of the PMO.Therefore, the right answer is B. [The environment in which project operates] [PMBOK 6th edition, Page 48]

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

There are no users currently online
top
Ā© 2019 OpenPM.org - All Rights Reserved