Dave is a project manager who manages a global project. He has stakeholders located in various parts of the globe. Due to the nature of the project, he also has large volumes of information he needs to share with the recipients. What type of communication method should he prefer for this purpose?

A. Pull communication.

B. Push communication.

C. Request-based communication.

D. Interactive communication.

1 responses on "PMP Exam Question 20"

  1. PMP Solution 20

    Pull communication is suited for this purpose. It is used for large volumes of information or for large audiences and requires the recipients to access communication content at their own discretion. Therefore the right answer is A. [PMBOK 6th edition, Page 374] [Project Communications Management].

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

There are no users currently online
top
Ā© 2019 OpenPM.org - All Rights Reserved