PMP Exam Question 2

Aligned with PMBOK 6th Edition®.

Schedule Risk Analysis

The Olympics are coming to your hometown. Transportation systems and venues are going to be upgraded. It has been decided that meeting the schedule is more important than minimizing cost at this point. Because a delay is unacceptable, we decide to use Monte Carlo to simulate the schedule. We most likely will run Monte Carlo simulations on a weekly basis. Which of the following is used as a model in a schedule risk analysis?

a) Work breakdown structure.

b) Schedule network diagram and duration estimates.

c) Project management plan.

d) Schedule management plan.

February 16, 2020

2 responses on "PMP Exam Question 2"

  1. PMP Solution 2

    Work Breakdown Structure (WBS) is the process of subdividing project deliverables and project work into smaller, more manageable components.
    When running a Monte Carlo analysis for schedule risk, the schedule network diagram and duration estimates are used. An integrated quantitative cost-schedule risk analysis uses both inputs. The output is a quantitative risk analysis model. Correct answer is b).[PMBOK 6th edition, Page 433] [Project Risk Management].

    Cheers

  2. B-Schedule network diagram and duration estimates.

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of Blanka Székely
© 2020 - All Rights Reserved.