A project charter that formally authorized a project was created. The project charter documented the initial requirements to satisfy stakeholders’ needs and expectations. How often should the project charter be revised?

A. At the beginning, middle, and end of a project.

B. Once a month.

C. Project charter is usually not updated during the course of the project.

D. As required by the PMO.

1 responses on "PMP Exam Question 18"

  1. PMP Solution 18

    Develop Project Charter is the process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. The key benefits of this process are that it provides a direct link between the project and the strategic objectives of the organization, creates a formal record of the project, and shows the organizational commitment to the project. This process is performed once or at predefined points in the project. Therefore, right answer is C. [PMBOK 6th edition, Page 75] [Project Integration Management].

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

Profile picture of Neeraj
top
Ā© 2019 OpenPM.org - All Rights Reserved