PMP Exam Question 17

Aligned with PMBOK 6th Edition®.

Decision tree analysis is used to calculate the average outcome when the future includes scenarios that may or may not happen. What are a decision node’s inputs and outputs?

A. Input: Cost of each decision; Output: Probability of occurrence

B. Input: Cost of each decision; Output: Decision made

C. Input: Scenario probability; Output: Expected Monetary Value (EMV)

D. Input: Cost of each decision; Output: Payoff

1 responses on "PMP Exam Question 17"

  1. PMP Solution 17

    Decision tree analysis is used to calculate the average outcome when the future includes scenarios that may or may not happen. In a decision node, the input is the cost of each decision and the output is a decision made. Therefore, right answer is B. [PMBOK 6th edition, Page 435] [Project Risk Management]. .

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

There are no users currently online
top
© 2019 OpenPM.org - All Rights Reserved