Due to your great success on your last project, you have been assigned to a new project with a very difficult customer. Based on lessons learned from others, you recognize that is critical that your project has well-defined acceptance criteria. Which of the following statements is false in regards to acceptance criteria?

a) Criteria includes performance requirements that must be achieved before acceptance of project deliverables.

b) Criteria is defined in the project scope

c) The fact that the deliverables meet the acceptance criteria means that customer needs have been satisfied.

d) Control Quality validates that the customer’s acceptance criteria has been met.

1 responses on "PMP Exam Question 14"

  1. PMP Solution 14

    The question is looking for the false statement. Formal acceptance validates that the customer’s needs have been met but not in the Control Quality process. The Validate Scope process differs from the Control Quality process in that the former is primarily concerned with acceptance of the deliverables, while the latter is primarily concerned with correctness of the deliverables and meeting the quality requirements specified for the deliverables. Therefore, right answer is d). [PMBOK 6th edition, Page 164] [Project Quality Management].

    Cheers

Leave a Message

Your email address will not be published. Required fields are marked *

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca
info@openpm.org

Who’s Online

There are no users currently online
top
© 2019 OpenPM.org - All Rights Reserved