Work Package :

You are the project manager in the development of a virtual reality device. One work package for the user interface deliverable should be inspected and compared to the acceptance criteria. Where could you find acceptance criteria for a work package?

A. WBS Dictionary.
B. Scope Management Plan.
C. Project Scope Statement.
D. Work Breakdown Structure.

2 responses on "PMP Exam Question 129"

  1. PMP® Solution 129.

    X B. The scope management plan is a component of the project management plan that describes how the scope will be defined, developed, monitored, controlled, and validated. The components of a scope management plan include: (…) – Process that specifies how formal acceptance of the completed project deliverables will be obtained. (But not the acceptance criteria itself for a work package).

    X C. The project scope statement is the description of the project scope, major deliverables, assumptions, and constraints. The detailed project scope statement, either directly or by reference to other documents, includes (…) – Acceptance criteria. A set of conditions that is required to be met before DELIVERABLES are accepted.

    X D. The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. Each descending level of the WBS represents an increasingly detailed definition of the project work.

    The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the WBS. The WBS dictionary is a document that supports the WBS. Most of the information included in the WBS dictionary is created by other processes and added to this document at a later stage. Information in the WBS dictionary may include but is not limited to: Code of account identifier, Description of work, Assumptions and constraints, Responsible organization, Schedule milestones, Associated schedule activities, Resources required, Cost estimates, Quality requirements, Acceptance criteria, Technical references, and Agreement information. Therefore, right answer is A. [PMBOK 6th edition, Page 162] [Project Scope Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of Meenakshi Sharma
Profile picture of Ramanand Bhat
Profile picture of Jaime Alonso Candau

© 2020 - All Rights Reserved.
OpenPM.org contains affiliate links, meaning at no additional cost to you, we will earn a commision if you click through and make a purchase.
OpenPM has never and will never compromise its integrity.

1