PMP Exam Question 126

Aligned with PMBOK 6th EditionĀ®.

Organizational Process Assets (OPAs) :

While preparing your schedule management plan, you are considering organizational process assets (OPAs) that could influence this process. Which of the following is an example of an organizational process asset in this process?

A. Organizational structure.
B. Team resource availability.
C. Commercial databases.
D. Lessons learned repositories.

2 responses on "PMP Exam Question 126"

  1. @JAIME ALONSO CANDAU,

    It is well understood that organizational structure and commercial database could be the Part of EEF.
    It is also understandable that Resource Availability cannot be an input while preparing schedule management plan, it could be an input for developing schedule.

    But how can be Resource availability be part of EEF? Resources availability are shown in resources calendars and they’re part of OPA.

    Please respond here or email me on [email protected], I want to clear out my doubt.

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

There are no users currently online
top

Ā© 2021 - All Rights Reserved - Nonica - OpenPM.org contains affiliate links, meaning at no additional cost to you, we will earn a commision if you click through and make a purchase. OpenPM has never and will never compromise its integrity.