PMP Exam Question 126

Aligned with PMBOK 6th Edition®.

Organizational Process Assets (OPAs) :

While preparing your schedule management plan, you are considering organizational process assets (OPAs) that could influence this process. Which of the following is an example of an organizational process asset in this process?

A. Organizational structure.
B. Team resource availability.
C. Commercial databases.
D. Lessons learned repositories.

1 responses on "PMP Exam Question 126"

  1. PMP Solution 126

    A. Organizational culture and structure are enterprise environmental factors (EEFs) that can influence the Plan Schedule Management process.

    B. Team resource availability and skills and physical resource availability are enterprise environmental factors (EEFs) that can influence the Plan Schedule Management process.

    C. Commercial databases, such as standardized estimating data are enterprise environmental factors (EEFs) that can influence the Plan Schedule Management process.

    The organizational process assets (OPAs) that can influence the Plan Schedule Management process include but are not limited to:
    -Historical information and lessons learned repositories;
    -Existing formal and informal schedule development, management- and control-related policies, procedures, and guidelines;
    -Guidelines and criteria for tailoring the organization’s set of standard processes and procedures to satisfy the specific needs of the project,
    -Templates and forms; and -Monitoring and reporting tools.
    Therefore, right answer is D. [PMBOK 6th edition, Page 180] [Project Schedule Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of Jaime Alonso Candau
Profile picture of Prakash Nagarajan
Profile picture of Praveen

© 2020 - All Rights Reserved.
OpenPM.org contains affiliate links, meaning at no additional cost to you, we will earn a commision if you click through and make a purchase.
OpenPM has never and will never compromise its integrity.

1