Project Requirements :

In your web development project, you are determining and managing project requirements and stakeholder needs by posing a question to the project management team, then a moderator writes down all ideas in a flip chart. Which interpersonal and team skill would enhance it with a voting process to rank the most useful ideas?

A. Autocratic decision making.
B. Multicriteria decision analysis.
C. Nominal group technique.
D. Influencing.

1 responses on "PMP Exam Question 123"

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of Wenz de la Serna
top

Ā© 2021 - All Rights Reserved - Nonica - OpenPM.org contains affiliate links, meaning at no additional cost to you, we will earn a commision if you click through and make a purchase. OpenPM has never and will never compromise its integrity.