PMP Exam Question 122

Aligned with PMBOK 6th EditionĀ®.

Triangular distribution :

You are estimating activity durations in the project you manage. You estimate 43 days as the most likely duration of an activity. In a best-case scenario, the activity will last 37 days and 55 days in the worst-case scenario. Based on triangular distribution, what is the estimated duration of that activity?

A. 36 days.
B. 41 days.
C. 44 days.
D. 45 days.

1 responses on "PMP Exam Question 122"

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of NewTest2022
top

Ā© 2021 - All Rights Reserved - Nonica - OpenPM.org contains affiliate links, meaning at no additional cost to you, we will earn a commision if you click through and make a purchase. OpenPM has never and will never compromise its integrity.