PMP Exam Question 119

Aligned with PMBOK 6th Edition®.

Quality Planning :

The project team and you are working on the quality management plan. There are two changes related to quality standards that require a detailed risk analysis. How should you perform this process?

A. In sequence with other planning processes and analyze risks after Plan Quality Management.
B. In parallel with other planning processes and analyze risks in the meantime.
C. You should focus on analyzing the two risks in the Executing Process Group.
D. You should have focused on analyzing all risks in the Initiating Process Group.

1 responses on "PMP Exam Question 119"

  1. PMP Solution 119

    C & D. From the process of identifying individual project risks as well as sources of overall project risk and documenting their characteristics in Identify Risks to the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks in Plan Risk Responses take part in the Planning Process Group.

    A & B. Quality planning should be performed in parallel with the other planning processes. For example, changes proposed in the deliverables in order to meet identified quality standards may require cost or schedule adjustments and a detailed risk analysis of the impact to plans. Therefore, right answer is B. [PMBOK 6th edition, Page 278] [Project Quality Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of UDAY
Profile picture of Isaline

© 2020 - All Rights Reserved.
OpenPM.org contains affiliate links, meaning at no additional cost to you, we will earn a commision if you click through and make a purchase.
OpenPM has never and will never compromise its integrity.