PMP Exam Question 117

Aligned with PMBOK 6th Edition®.

Project Management Components :

In your construction project, the project sponsor would like to know when the project progress will be reviewed to determine if performance is as expected and if preventive or corrective actions are necessary. What project management component include that information?

A. Schedule baseline.
B. Configuration management plan.
C. Performance measurement baseline.
D. Management reviews.

1 responses on "PMP Exam Question 117"

  1. PMP Solution 117

    A. The Schedule Baseline is the approved version of the schedule model that is used as a basis for comparison to the actual results.
    B.Configuration management plan describes how the information about the items of the project (and which items) will be recorded and updated so that the product, service, or result of the project remains consistent and/or operative.
    C. Performance measurement baseline is an integrated scope-schedule-cost plan for the project work against which project execution is compared to measure and manage performance.

    The project sponsor would like to know when. Management reviews identifies the points in the project when the project manager and relevant stakeholders will review the project progress to determine if performance is as expected, or if preventive or corrective actions are necessary. Therefore, right answer is D. [PMBOK 6th edition, Page 88] [Project Integration Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of Claudia
Profile picture of Jaime Alonso Candau
Profile picture of PRAMILA SHARMA
Profile picture of Ignatious Benedict
Profile picture of jim

© 2020 - All Rights Reserved.
OpenPM.org contains affiliate links, meaning at no additional cost to you, we will earn a commision if you click through and make a purchase.
OpenPM has never and will never compromise its integrity.