Before initiating a project :

Matt, as project manager, and the project sponsor are going to review high level strategic and operational assumptions in a project before it is initiated. Which document should include that information?

A. Issue log.
B. Assumption log.
C. Business case.
D. Requirement register.

1 responses on "PMP Exam Question 105"

  1. PMP Solution 105

    A.The issue log will help the project manager effectively track and manage issues, ensuring that they are investigated and resolved. The issue log is created for the first time as an output of this process, although issues may happen at any time during the project.
    B. Lower-level activity and task assumptions are generated throughout the project such as defining technical specifications, estimates, the schedule, risks, etc. The assumption log is used to record all assumptions and constraints throughout the project life cycle.
    D. This is not a document defined in PMBOK 6th Edition.

    High-level strategic and operational assumptions and constraints are normally identified in the business case before the project is initiated and will flow into the project charter. Therefore, right answer is C. [PMBOK 6th edition, Page 81] [Project Integration Management]

    Cheer

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of Samruddhi Sudhakar Shetty
Profile picture of Imen MLIKA
Profile picture of Muhammad Elemam
© 2020 - All Rights Reserved.