PMP Exam Question 104

Aligned with PMBOK 6th EditionĀ®.

PMP Material Grading :

Jodie is the project manager in the development of a new electronic device. Her device requires a low grade material for inside pieces but a specific high grade material for exposed surfaces certified by a manufacturer. Which project document includes that information?

A. Quality report.
B. Resource Management Plan.
C. Activity Attributes.
D. Resource Breakdown Structure.

February 16, 2020

4 responses on "PMP Exam Question 104"

  1. PMP Solution 104

    A.The quality reports include information provided that can be used by other processes and departments to take corrective actions in order to achieve the project quality expectations. It may include; recommendations for process, project, and product improvements; corrective actions recommendations (including rework, defect/bugs repair, …); and the summary of findings from the Control Quality process. However, no information about grading materials or required certifications is included in this document.
    B. The resource management plan is the component of the project management plan that provides guidance on how project resources should be categorized, allocated, managed, and released. It may include; Identification of resources, Acquiring resources, Roles and responsabilities, Project organization charts, Project team resource management, Training, Team development, Resource control and Recognition plan.
    C. Activity attributes extend the description of the activity by identifying multiple components associated with each activity. The components for each activity evolve over time. During the initial stages of the project, they include the unique activity identifier (ID), WBS ID, and activity label or name.

    The resource breakdown structure is a hierarchical representation of resources by category and type. Examples of resource categories include but are not limited to labor, material, equipment, and supplies. Resource types may include the skill level, grade level, required certifications, or other information as appropriate to the project. Therefore, right answer is D. [PMBOK 6th edition, Page 326] [Project Resource Management]

    Cheers

Leave a Message

About

Welcome to the First OPEN Project Management Community. Forever FREE PMP Resources; Exam Simulators, PMP Progress Tracking, Weekly Exam Questions, ...

Palma de Mallorca

[email protected]

Who’s Online

Profile picture of Lawman
Ā© 2020 - All Rights Reserved.