Project Schedule Management

4.4( 9 REVIEWS )
1532 STUDENTS

Project Schedule Management: 21 PMP Exam Questions

In this course, I have carefully prepared for you 21 PMP Exam Questions from the Project Schedule Management knowledge area of the PMBOK.

These questions could be part of your PMP Exam.

All of them are aligned with the last version of PMBOK (6th edition).

I hope they can help you pass your PMP Exam.

 

Sincerely,

Course Curriculum

Project Schedule Management
Project Schedule Management Exam 1 00:25:12

Course Reviews

4.4

4.4
9 ratings
  • 5 stars4
  • 4 stars5
  • 3 stars0
  • 2 stars0
  • 1 stars0
  1. 4

    Thank you for this WONDERFUL asset and resource, truly a great site.

  2. 4

    Thank you for basic knowledge questions.
    Website a bit slow and take run time during Q/A and submit the result.

  3. Great review for schedule...

    4

    However question 19 should have the answer: C 11.0 weeks. This is because we need to add 1 to the calculation since the formula is: duration = EF – ES + 1. This can be confirmed by referring to the diagram on page 211 on the PMBOK. Other than that, this was a great review… (Correct this minor issue and I would rate this 5 stars.)

    The GHANTT chart question tripped me up nicely. Thank you for making me realize gaps in my basic knowledge of scheduling.

  4. REPLY TO GREAT REVIEW FOR SCHEDULE

    5

    Hi Rick,

    Thanks for your comment! We have reviewed the question and added “Please use the accepted convention of the project starting on day 1 for calculating start and finish dates.” Also the solution has been reviewed to meet that accepted convention..

    Thanks for helping us improving this community.
    Regards,
    Jaime

  5. Question 16 - Calculation of Most Likely Duration

    4

    Excellent set of questions. However, I believe solution to Question 16 is incorrect.
    Question:
    Using beta distribution, find out the most likely activity duration, in a project with an expected duration of 5 weeks, an optimistic duration of 4 weeks and a pessimistic duration of 8 weeks.
    Answer provided is 5.33 weeks which would be correct if the question was to compute Expected Duration (tE) based on tM, tO, tP.
    In this case, following parameters are already provided in the question:
    Expected Duration tE = 5
    Optimistic Duration tO = 4
    Pessimistic Duration tP = 8
    We need to compute most likely Duration now using BETA distribution:
    tE = (tO+4xtM+tP)/6
    Hence, tM = (6xtE – tO – tP)/4 = 4.5 weeks

    Please review this and clarify. It is a very good trick question, but answer provided is incorrect

  6. Manoj Reply

    5

    Hi Manoj,

    Thanks for your message. We are glad that you share your concern with us.. The question asks for the activity duration, so for clarity we have review the sentence of the question to avoid any other confusion.

    Thank you

1532 STUDENTS ENROLLED

THE BEST PM COURSES ONLINE


Tested & Reviewed by OpenPM

© 2020 - All Rights Reserved - Nonica - OpenPM.org contains affiliate links, meaning at no additional cost to you, we will earn a commision if you click through and make a purchase. OpenPM has never and will never compromise its integrity.

1